Victoria's Guide to Standards and Tolerances has been replaced. In the new edition's 127 technical clauses, "builder" and "owner" appear twice.

The 2026 edition commenced on 1 August 2026 and is not retrospective. This is a clause-by-clause comparison with the 2015 edition it supersedes — what changed, what didn't, and which edition applies to the job in front of you.

Published: 1 August 2026
Where: Victoria
Read time: ~10 min
A Site Inspections inspector on site with measuring equipment, alongside the cover of the Guide to Standards and Tolerances 2026
Photo: Site Inspections. Shown with the cover of the Guide to Standards and Tolerances 2026, published by the Building and Plumbing Commission.
Key facts
Document
Guide to Standards and Tolerances 2026
BUI-QRG-001 · 50 pages
Published
31 July 2026
BPC resource hub
Commenced
1 August 2026
Not retrospective
Applies to
Contracts from 1 Aug 2026
Or work commencing on or after that date
Previous edition
2015 · 70 pages
Superseded still governs earlier jobs
Revised by
Office of the State Building Surveyor
With BPC dispute resolution and insurance divisions
Key takeaways
The 2026 edition commenced on 1 August 2026 and does not apply retrospectively. Two editions are now in play, and the contract date decides which one governs.
Every clause was rewritten from "is defective if…" to "is not within tolerance if…". The phrase "is defective" appears 74 times in the 2015 edition and is gone as a test in 2026.
Across 127 technical clauses, the words "builder" and "owner" appear twice. Fault and causation language has largely left the document.
Some tolerances moved. Building dimensions went from 5 mm to 10 mm, tile flatness tightened from ±4 mm to ±3 mm, and the AS 2870 damage-category tables were replaced by single thresholds.
14 clauses are new and 13 were removed — including the timber-framing shrinkage table, dry valley construction, stair treads and risers, and the plumbing compliance certificate.

01What changed, and when

A new edition, a new commencement date, and two editions running side by side.

The Building and Plumbing Commission published a new edition of the Guide to Standards and Tolerances on 31 July 2026. It commenced the following day.

The new edition applies to domestic building contracts entered into, or building work that commences, on or after 1 August 2026. It does not apply retrospectively. For contracts entered into or work commenced before that date, the 2015 edition still governs — the BPC's own page directs readers to the previous version for those jobs, while listing it under superseded versions. Two editions are live at once, and the contract date decides which one applies.

The document has also changed shape. The 2015 edition ran to 70 pages across 18 numbered items. The 2026 edition runs to 50 pages, restructured into three parts: Part A background, Part B measurement and inspection, and Part C the technical content — 21 sections holding 127 numbered clauses.

It was revised by the Office of the State Building Surveyor, in consultation with the BPC's dispute resolution and insurance divisions. The 2015 edition was produced by the Victorian Building Authority; the 2026 edition is described as the property of the Victorian Government.

30 March 2015
2015 edition takes effect
Applies to domestic building contracts entered into from this date.
1 July 2025
BPC replaces the VBA
The Building and Plumbing Commission becomes Victoria's building regulator.
14 July 2026
2026 edition dated
Document reference BUI-QRG-001.
31 July 2026
Published
Listed on the BPC resource hub; the 2015 edition moves to superseded versions.
1 August 2026
Commences
Applies prospectively only, to contracts entered into or work commencing on or after this date.

02How the regulator describes the change

The BPC's own summary, in full, before anything else.

"This edition includes updates to improve clarity, readability and consistency, together with refreshed references and guidance to better support consumers and industry in understanding acceptable standards and tolerances."

Building and Plumbing Commission
Guide to Standards and Tolerances 2026 resource page · 31 July 2026

The same page is explicit about what the Guide is not. It states the Guide "is not legislation, a building contract or a technical construction manual", that it does not replace legislation, the National Construction Code, Australian Standards or contractual obligations, and that it "should not be used to determine whether building work complies with regulatory requirements".

It also sets out how the regulator uses it: the BPC "uses the Guide as a recognised reference when responding to enquiries and supporting the resolution of domestic building disputes".

Why the detail matters
This is the document the regulator reaches for when a dispute lands on its desk. Changes to it change the reference point for those conversations.

03From "defective" to "not within tolerance"

The most visible change is the language, and it runs through every clause.

The 2015 edition framed every clause as a defect test. The phrase "is defective" appears 74 times. Work either was defective or it wasn't.

The 2026 edition frames every clause as a tolerance test. The phrases "not within tolerance" and "outside tolerance" appear 195 times between them. "Defective" no longer appears as a test anywhere in the technical content.

2015 edition

"is defective if…"

Used 74 times
Work is defective, or it is not
Quotes the Domestic Building Contracts Act definition of "defective" in full
2026 edition

"not within tolerance"

Used 195 times
Work sits inside a tolerance, or outside it
States its purpose is to assist in determining whether work is defective for the purpose of section 8 of that Act

One thing did not change, despite appearances: the Guide's status. Both editions state plainly that it sits outside the regulatory hierarchy. The 2015 edition said it "is only a guide and an advisory document. It is not a regulated standard and is not part of this hierarchy." The 2026 edition says it "is only an advisory document. It is not part of the Victorian legislative framework."

What did change is the framing of its purpose. The 2026 edition adds that the intention is "to facilitate the resolution of disputes and not provide the definitive determination of whether building work is considered defective."

04Fault, causation and contract deference

The change that does not appear in the summary, and it runs through the whole document.

16
clauses opened "unless documented otherwise" in 2015
zero in 2026
2
mentions of "builder" or "owner"
across 127 technical clauses
8
explanatory notes removed
all of them
28
uses of "handover" in 2015
replaced by a defined "completion"
Figure 1 · Fault, deference and timing language — occurrences in each edition
"unless documented otherwise"16 → 0
"handover" as the reference point28 → 0
"caused by the builder"6 → 0
"due to the builder"6 → 0
"responsibility of the owner"5 → 0
"owner is responsible"3 → 0
"maintenance period"5 → 0
explanatory notes8 → 0
2015 edition
2026 edition — every bar is zero

The 2015 edition opened clauses with a contract-deference qualifier 20 times — "unless documented otherwise" sixteen times, plus three related variants. The 2026 edition uses none of them. Part A still states that legislation and the building contract take precedence generally, but the clause-by-clause deference is gone.

Fault language went the same way. The 2015 edition attributed defects to the builder or excused the owner repeatedly: "caused by the builder" six times, "due to the builder" six times, "responsibility of the owner" five times, "owner is responsible" three times. It also carried a dedicated section on responsibility to rectify, with five worked examples of where liability sat between builder and owner.

In the 2026 edition's 127 technical clauses, the words "builder" and "owner" appear twice — once at clause 3.2 (footings and slabs, referring to "poor site management by the builder") and once at clause 21.5 (building maintenance, referring to "whether the matter relates to the builder's workmanship or general building use").

The "documented maintenance period" concept has gone entirely, replaced by fixed periods running from completion. And "handover" — the 2015 edition's reference point — has been replaced by "completion", now defined by reference to section 42 of the Domestic Building Contracts Act, the issue of an occupancy permit or certificate of final inspection, or completion under the contract. Handover and completion are not necessarily the same date.

The fair reading
There is a coherent explanation for this. The 2026 edition states expressly that allocation of responsibility to rectify is beyond the Guide's scope. Removing fault language is internally consistent with that narrower remit — the Guide now describes the physical state of the work, and fault is argued under the contract, the Domestic Building Contracts Act, and at VCAT instead. The practical consequence is the same either way: establishing that work sits outside tolerance no longer requires establishing who caused it.

05Clause by clause

Nine pairs, quoted directly from both editions. Clause numbers are given so each can be checked in the source.

Roof tiles2015 cl 6.03 → 2026 cl 8.3
2015 edition
"Roof tiles are defective if they do not conform to the manufacturer's sample. Irregularities in tiles are defects if they are visible from a normal viewing position at ground or upper floor levels. Minor surface marks or blemishes arising from the tile manufacturing process are not defective. Cracked or broken roof tiles are defective if caused by the builder's workmanship."
2026 edition
"Roof tiles are not within tolerance if they are cracked or broken, or significant irregularities in tile appearance are visible from a normal viewing position at ground or an upper floor level. Where roof tiles are obtained from different batches, they are to be blended where practicable, to minimise variations in colour, texture, and pattern. Manufacturer's installation instructions and display panels may guide with tolerance identification. Minor surface marks or blemishes arising from the tile manufacturing process are within tolerance."
ChangeThe causation test is gone. A cracked tile is now outside tolerance on its face, without asking who caused it.
Cracked, chipped or loose tiles2015 cl 11.05 → 2026 cl 14.3
2015 edition
"Tiles are defective if they are cracked, pitted, chipped, scratched or loose at handover. After handover, tiles are defective where the builder's workmanship causes the tiles to become cracked, pitted, chipped or loose within 24 months."
2026 edition
"Tiles are not within tolerance if they are cracked, pitted, chipped, scratched or loose at completion."
ChangeThe entire second sentence has no counterpart. The 24-month post-completion window is gone.
Springy floors2015 cl 14.07 → 2026 cl 15.7
2015 edition
"Floors that bounce in a way that can be detected by a person walking normally in a trafficable area are defective if the substructure has not been constructed in accordance with the Building Code of Australia and AS 1684."
2026 edition
"Floors that bounce in a way that can be detected by a person walking normally across the area are not within tolerance."
ChangeA compliance test became a performance test. The bounce alone now decides it.
Wall cladding and corrosion2015 cl 5.02 → 2026 cl 7.1
2015 edition
"Staining, folds, splits, dents, open joints between panels, cracking and other distortions in wall cladding are defective if they are visible from a normal viewing position at ground level or an upper floor level. Any unintended corrosion of metal wall cladding is defective unless it is due to lack of maintenance by the owner."
2026 edition
"Wall cladding is not within tolerance if staining, folds, splits, dents, open joints between panels, cracking and other distortions are visible from a normal viewing position at ground level or an upper floor level. Deterioration of wall cladding, including metal corrosion, is outside tolerance if the wall cladding is exposed to normal environmental conditions and does not achieve the service life specified by the manufacturer."
ChangeThe owner-maintenance excuse is replaced by an objective test against the manufacturer's stated service life.
Door furniture2015 cl 8.03 → 2026 cl 11.3
2015 edition
"During the documented maintenance period after completion, handles, locks and latches are defective if they do not operate as intended by the manufacturer. If the maintenance period is not documented, three months is the assumed time period after completion. After the end of the maintenance period, failure is not a defect unless it is caused by the builder's workmanship or a faulty product supplied by the builder."
2026 edition
"Door furniture including handles, locks and latches is not within tolerance if they do not operate as intended 3 months after completion."
ChangeThe contract-set maintenance period and the protection that followed its expiry are both gone, replaced by a flat three months.
Termite damage2015 cl 18.07 → 2026 cl 21.3
2015 edition
"Damage caused by termites that occurs in areas not designated by the relevant council as a termite risk area is the responsibility of the owner. Damage caused by termites in buildings within designated termite risk areas is defective if the termite management system has not been installed in accordance with the Building Code of Australia. Damage caused by termites in buildings within designated termite risk areas is not defective if the termite management system has not been regularly maintained by the owner, made non-compliant by the owner after handover, or not maintained in accordance with the manufacturer's instructions and AS 3660.2."
2026 edition
"Damage caused by termites is outside tolerance if the building is located in an area designated as a termite risk area by the council, and the termite management system was not installed in accordance with AS 3660.1 Termite management - New building work."
ChangeThree limbs became one. The owner-maintenance carve-out is gone, and the referenced standard moved from AS 3660.2 (existing buildings) to AS 3660.1 (new work).
Leaks in roofing2015 cl 6.01 → 2026 cl 8.1
2015 edition
"Roofing, including flashings and accessories, is defective if it leaks under normal weather conditions and is due to the builder's workmanship, causes unhealthy or dangerous conditions, loss of amenity for occupants, undue dampness or deterioration of building elements."
2026 edition
"Roof cladding, flashings and accessories are not within tolerance if unintended dampness or deterioration of building elements occurs due to leaking under normal environmental conditions."
ChangeThe workmanship limb and the amenity limbs are gone. Dampness or deterioration from a leak is now the whole test.
Electrical2015 cl 15.01 → 2026 cl 19
2015 edition
"Any electrical work is defective if it does not comply with the relevant regulations or the contract documents. The builder shall provide the owner with a Certificate of Electrical Safety when a certificate is required to be issued by the licenced electrician."
2026 edition
"Electrical work is not within tolerance if a product or any fixture or fitting appears out of level or inconsistent with similar installations when viewed from a normal viewing position."
ChangeThe compliance test and the certificate requirement are both gone. What remains is an appearance test. Electrical compliance itself continues to sit with the electrical regulations, outside this Guide.
Foundation movement after occupation2015 cl 2.01 → 2026 cl 3.2
2015 edition
"The builder is not responsible for foundation movement caused by activities that were not documented at the time of entering into the contract or as variation to that contract, or that are undertaken by the owner. These include paving, landscaping, planting trees and drainage works after the site is handed over to the owner. The builder is not responsible for foundation movement caused by the owner's failure to maintain drainage systems after the site is handed over to the owner."
2026 edition
No equivalent clause. The nearest text runs the other way: "Footings and slabs are not considered to be within tolerance where failure results from foundation movement caused by poor site management by the builder, including inadequate site drainage during construction."
ChangeAn express builder protection was not carried forward. The 2026 edition addresses the builder's own site management instead, and says nothing about the owner's landscaping, trees or drainage.

06The numbers that moved

Not everything is drafting. Several tolerances changed value.

Item
2015
2026
Direction
Building dimensions — minimum
the greater of the ratio or 5 mm
the greater of the ratio or 10 mm
Looser
Slab cracking
AS 2870 categories 0–4; defective at Category 3
2 mm single threshold
Simplified
Masonry cracking
AS 2870 categories; under 5 mm defective requiring repair
5 mm threshold; under 5 mm expressly within tolerance
Looser
Tile flatness
±4 mm in 2 m
±3 mm in 2 m
Tighter
Frame straightness
4 mm in any 2 m
5 mm from a 2 m straight edge
Looser
Frame plumbness
5 mm over 1.8 m
5 mm over 2 m
Looser
Door bowing across width
2 mm
3 mm
Looser
Voids in mortar
defective if visible
visible and over 5 mm diameter
Looser
Window and door installation
no tolerance stated
5 mm over 1800 mm
New
Glazing blemishes
visible from a normal viewing position
visible from 3 m; ≤10 mm and ≤3 per pane within tolerance
New
Tile lippage
2 mm; 1.5 mm ground-flat; 1 mm at joints ≤3 mm
Five-row table keyed to surface profile and joint width (1.0–2.0 mm)
Restructured
Tiling movement joints
Spacings given — 4.5 m centres; internal >9 m, or >6 m in sunlight; external >4.5 m
General requirement, no spacings stated
Reduced
Concrete pavement
Three AS 3727 criteria — crack ≤1.5 mm, subsidence ≤15 mm under a 3 m straight edge, stepping ≤5 mm
Cracking or subsidence over 1.5 mm within 12 months
Simplified
Masonry construction table
12 items, structural and non-structural columns
6 diagrams
Reduced
Carried into the 2026 diagrams
Horizontal position at base or storey — 15 mm
Step of an exposed surface — 2 mm
Bed joint from horizontal — ±10 mm / 10 m · ±15 mm total
Bed joint thickness — 10 mm ±3 mm
Perpend thickness — 10 mm ±5 mm
Cavity width · brick overhang — 15 mm
No longer stated in the Guide
Displacement between loadbearing walls in adjacent storeys — 10 mm
Deviation from plumb within a storey — lesser of 10 mm per 3 m or 0.05 × leaf thickness
Deviation from plumb over total building height — 25 mm
Bow of a masonry surface in any 2 m — 5 mm structural / 3 mm non-structural
Maximum difference in perpend thickness — 8 mm
The structural vs non-structural distinction itself

The masonry reduction is worth its own note. The 2015 edition reproduced AS 3700's tolerance table in full. The 2026 edition keeps six items as diagrams — horizontal position, step of exposed surface, bed joint level and thickness, perpend thickness, and cavity width — and refers readers to Part 12.5 of AS 3700 for the rest. Wall plumbness within a storey, plumbness over total building height, masonry bow, and the maximum difference in perpend thickness are no longer stated in the Guide. They remain in AS 3700.

Light steel framing gains its own tolerances throughout for the first time: plumbness of height/600 or 3 mm, straightness of 5 mm from a 3 m straight edge, truss bow of L/500, and truss plumbness of the lesser of height/100 and 20 mm.

Figure 2 · Documents listed in the reference schedule
26 13 2015 edition 2026 edition

The reference schedule halved. AS 1684 (residential timber-framed construction), AS 3740 (waterproofing of domestic wet areas), AS 4654 (waterproofing membranes for external above-ground use), AS 2047 (windows in buildings), AS 4773.2 (masonry in small buildings), AS/NZS 3500.3 (stormwater drainage), AS/NZS 4386.1 (domestic kitchen assemblies) and AS 1860.2 (particleboard flooring installation) are not referenced anywhere in the 2026 edition. Neither are the four CSIRO building technology files or the ABCB condensation handbook.

These standards still apply
They continue to operate through the National Construction Code and the Regulations. What changed is that this Guide no longer points to them. Newly referenced: AS 2688 (timber and composite doors) and AS 3959 (construction in bushfire-prone areas). AS 3660.2 has been replaced by AS 3660.1.

One further change sits in Part A. The 2015 edition said the applicable edition of a referenced standard is the one current when the contract was signed. The 2026 edition says it is the edition published at the time building work commenced. On a job where those dates are a year apart and the standard was reissued in between, that is a different document.

07What's new in 2026

Fourteen clauses have no counterpart in the 2015 edition, plus four changes to how the Guide is applied.

3.7
Falls in external concrete floors
Stormwater must drain to the slab edge or a drainage system
5.8
Recycled and reclaimed bricks
Guide tolerances may not be appropriate
5.18
Efflorescence in masonry
Treated as a possible moisture-control indicator
7.3
External timber trims
Outside tolerance if loose within 12 months
9.7
UV protection for PVC and PE pipes
Exposed pipes must be shielded or UV-protected
11.9
Glazing
Moved from General and quantified — 3 m viewing distance
12.2.10
Straightness of plasterboard ceilings
4 mm from a 2 m straight edge
13.10
Sealing of benchtop cut edges
Includes cut-outs for sinks and appliances
15.9
Carpet, vinyl and floating floors
Its own clause; movement noise is within tolerance
17.2
Decks — wind driven water
Replaces the 2015 freeboard and upstand clause
17.5
Durability of exposed timberwork
Splitting, bowing or cupping within 3 months
17.6
Eave and external ceiling linings
Outside tolerance if loose within 12 months
18.4
Water tanks
Leaks, base movement and overflow washout
21.5
Building maintenance
General, where 2015's was foundations-only

Four changes affect how the Guide is used rather than what it measures.

New rules of application
Complex slabs are excluded. Suspended, pre- and post-tensioned and pre-cast systems "should not be assessed under this Guide" — expert engineering guidance is to be sought instead. The Guide now covers simple in-situ slab-on-ground only.
Livable Housing Design takes precedence on internal dimensions, which may set minimum path-of-travel widths measured to the finished surface.
Digital and laser levels are expressly permitted. The 2015 edition illustrated measurement with a spirit level only.
A definitions table has been added — including "completion", "applicable building standard", "tolerance" and "non-critical light". The 2015 edition defined "builder" and "defective" inline but had no table.

08What was removed

Thirteen items in the 2015 edition have no counterpart in 2026. Several were the only place a number appeared.

2.09
Dimensions of building elements
Beams and posts — L/200 or 5 mm
3.19
Brick sills and the timber shrinkage table
AS 4773.2 eaves clearance table, six frame types
3.10
The crazing carve-out
Manufacturing surface cracks were not defective unless the unit fractured
4.04
Packing thickness limit
Total packing over 20 mm under bearers
4.06
Treads and risers in timber stairs
Including the 5 mm consistency allowance
4.07
Slab-edge fixing distances
50–70 mm from the edge; 5× fastener diameter
6.07
Dry valley construction
No equivalent anywhere in 2026
7.01
Plumbing compliance certificate
Builder to provide the plumber's certificate
11.02–11.04
Tiling responsibility allocation
Who bears failure when the owner supplies or lays tiles
9.13
The printed Level 4 definition
2026 references AS/NZS 2589 without reproducing it
14.03
Written-acknowledgement carve-out
Excess floor gaps were not defective if the owner was warned in writing
13.03
Five-year silicone note
Sealant replacement as owner maintenance
8.05
Two door distortion rows
Doors over 2400 mm (7 mm) and meeting-edge misalignment (5 mm)
Removed from the Guide is not removed from the law
Several of these sit in standards that still apply through the NCC and the Regulations — stair geometry, slab-edge fixings and plumbing certification among them. What changed is that this Guide no longer states them, so the number now has to be sourced from the standard or the Regulations directly.

09What didn't change

Plenty didn't move, and it is worth knowing before anyone re-measures a job.

Item
Value, both editions
Concrete floor levels
10 mm in any room or area · 4 mm in any 2 m · 20 mm across the footprint · 24 months
Timber floor levels
Same as concrete
Floor levels after restumping
15 mm in any room or area · 8 mm in any 2 m · 24 months
Stump plumbness
10 mm to 1 m · L/100 to 2 m · 20 mm at 2 m and over
Perpend vertical alignment
20 mm per 2 m height
Bed joint horizontal alignment
±10 mm in any 10 m · ±15 mm total
Raking of joints
10 mm depth
Wall surface bow
5 mm from a 1.8 m straight edge
Plasterboard finish
Level 4 to AS/NZS 2589
Plasterboard and cornice cracks
1 mm within 24 months
Cracking at dissimilar materials
1 mm within 12 months
Cornice straightness
4 mm from a 2 m straight edge
Internal door clearances
2–5 mm · not more than 20 mm to the floor finish
Roof overhang
Tiles 35–65 mm · sheet 50–65 mm
Roof undulation
20 mm over 4 m
Gutter water retention
10 mm
Gutter laps
25 mm
Flashings into masonry
15 mm
Timber floor lippage
0.5 mm
Paint durability
Same five-row table
Pool dimensions and datum
L/100 or 5 mm · 40 mm

Two measurement rules also carried across intact. The rule against interpolating tolerances — that a 4 mm deviation stated over 2 m applies equally over 1 m or 500 mm, and cannot be scaled down — appears in both editions, at Part E in 2015 and Part B in 2026. So do the datum rules for measuring horizontal and vertical surfaces.

The normal viewing position is unchanged at 1.5 m, and 600 mm for appliances and fixtures. The 2026 edition adds a third distance: 3 m for glass. It also now expressly permits digital or laser levels, where the 2015 edition illustrated measurement with a spirit level only.

10Which edition applies to your job

The contract date decides it.

Working out which Guide governs
The 2026 edition is not retrospective. Under the BPC's stated position, the test is the date of the contract, or where there is no contract, the date the work commenced.
Find the contract date. Signed on or after 1 August 2026, the 2026 edition applies. Signed before, the 2015 edition applies.
Where there is no contract, use the date the building work commenced.
Read the clause, not the summary. The two editions use different language for the same subject matter, and several tolerances changed value.
Check the standard behind the clause. Where the Guide no longer references a standard, that standard may still apply through the NCC or the Regulations.

Both editions remain available on the BPC's resource hub — the 2026 edition on its own page, and the 2015 edition listed there under superseded versions.

11Sources

Every comparison in this article was made by reading both editions in full. Clause numbers are cited so any reader can verify each quotation in their own copy.

1.
Guide to Standards and Tolerances 2026 — Building and Plumbing Commission
Published 31 July 2026, commenced 1 August 2026. Document reference BUI-QRG-001, 50 pages, dated 14 July 2026. bpc.vic.gov.au/resource-hub/guides/guide-to-standards-and-tolerances-2026
2.
Guide to Standards and Tolerances 2015 — Victorian Building Authority
70 pages, applicable to contracts entered into from 30 March 2015. Listed by the BPC as a superseded version. bpc.vic.gov.au/resource-hub/guides/guide-to-standards-and-tolerances-2015-under-review-2024
3.
AS 2870 Residential slabs and footings
Referenced by both editions for classification of damage due to foundation movement (Appendix C).
4.
AS 3700 Masonry structures
Part 12.5, referenced by the 2026 edition for tolerances in masonry construction.
General information, not legal advice. This article is our reading of two published documents — refer to the Guides themselves for the official text, and to the legislation, the National Construction Code and the applicable Australian Standards for binding requirements.