4.9 stars · 197 reviews · 24hr reports
Large modern Australian two-storey home with double garages and a circular driveway. Editorial illustration; it does not depict the property in this matter.
Court Cases
Case file · Supreme Court of Victoria
They fired their builder over defective work. The Supreme Court found the owners repudiated the contract, and ordered them to pay $697,805.

The court agreed the work was partly defective and allowed $574,380 to fix it. The owners still lost, and their counterclaim was dismissed. The whole case turned on fifteen days in April and May 2021.

Published: 20 August 2026
Where: Supreme Court of Victoria
Read time: ~9 min
A large modern Australian two storey home with double garages either side and a circular driveway
Editorial illustration Cover image generated for editorial illustration only. It does not depict the actual persons or property involved in this matter.
Key facts
Case
Hale Corp Pty Ltd v Ng
[2026] VSC 492
Court
Supreme Court of Victoria
Stynes J · Technology, Engineering and Construction List
Judgment
31 July 2026
heard over seven days in October 2025
Contract sum
$6,553,759.42
ABIC major works contract, February 2019
Awarded to the builder
$697,805.38
including GST
Owners' counterclaim
Dismissed
costs reserved
Key takeaways
The owners were right that there were defects. The court allowed $574,380.41 to rectify them. They still lost, because being right about the work is a different question from being entitled to terminate.
A notice to remedy default is not a countdown to termination. The builder answered it. Once it was answered, the ground for terminating was gone.
Where the actual cost of rectification was unavailable, the court accepted an expert's estimate as the evidence of cost. The report was not background material. It was the proof.
One defect was real and the rectification was out of all proportion to the benefit. With no evidence of what the defect did to the value of the property, the award was ten dollars.

01What it cost

The owners ended the contract. Five years later the court worked out who owed whom.

Two owners engaged a registered domestic builder to build a large two-storey home on a site at Bulla, in Melbourne's north. The contract sum was $6,553,759.42. Construction ran through 2019, 2020 and 2021, across the COVID-19 period.

The relationship broke down. The owners issued a notice to remedy default, then a notice of termination. The builder treated that termination as a repudiation of the contract, accepted it, and sued.

$697,805.38
Awarded to the builder
including GST
$574,380.41
Deducted for defective work
the owners were right about this part
Dismissed
The owners' counterclaim
costs reserved to a later date

The arithmetic in the reasons runs to a sub-total of $1,272,185.79 including GST, less $574,380.41 including GST for the cost of rectifying defective work, leaving $697,805.38.

Stynes J[917]
Subject to any submissions from the parties as to arithmetic error and in relation to the precise form of order, I propose to make orders to the effect that: (a) Hale is entitled to damages in the sum of $697,805.38 (incl GST). (b) The Owners' counterclaim is dismissed.
Hale Corp Pty Ltd v Ng [2026] VSC 492, 31 July 2026

02How it unfolded

The termination sequence took fifteen days. The proceeding took more than five years.

22 February 2019
Contract signed
An ABIC major works contract for housing in Victoria, for a contract sum of $6,553,759.42. The owners appointed an architect to administer the contract.
27 May 2019
The builder takes possession
The date for practical completion was initially 21 June 2020. It was later adjusted under the contract to 12 April 2021, and that adjusted date was not in dispute.
20 April 2021
Notice to remedy default
Eight days after the adjusted completion date. The builder responded to the notice, or otherwise sought to remedy the alleged defaults.
5 May 2021
The owners terminate
Fifteen days after the notice to remedy default, the owners sent a notice of termination.
3 June 2021
The builder accepts the repudiation
The builder treated the owners' purported termination as a repudiation of the contract, accepted it, and served its own notice of termination.
31 August 2021
A replacement builder is engaged
After a tender process of roughly two months. The replacement builder started on 5 October 2021 and finished on 29 March 2023, close to two years later.
10 April 2022
Proceedings begin at VCAT
The owners filed their defence and counterclaim in December 2022. In May 2024 the tribunal struck the proceeding out and referred it to the Supreme Court, observing that the resources required made that court the more appropriate forum.
31 July 2026
Judgment
Handed down after a seven day trial in October 2025. Five years and two months after the contract was terminated.

03Fifteen days

The notice to remedy default was answered. That is what decided the case.

A notice to remedy default is a step in a contractual process. It puts the builder on notice of an alleged default and gives it the opportunity to answer. What it is not is a countdown that entitles the owner to terminate when it expires.

The builder here responded to the notice, or otherwise sought to remedy the alleged defaults. The court was not satisfied that the owners were then entitled to terminate.

Stynes J[871]–[873]
For the reasons I have given, I am not satisfied that the Owners were entitled to terminate the Contract as they purported to do.

Hale asserts that by their attempt to terminate the Contract, the Owners repudiated the Contract. Hale says it accepted that repudiation so as to terminate the Contract at Common Law.

I agree, the conduct of the Owners demonstrated a clear intention no longer to be bound by the Contract. Hale, as the innocent party was entitled to accept that repudiation and to sue for damages.
Hale Corp Pty Ltd v Ng [2026] VSC 492, 31 July 2026
The trap in one sentence

An owner who terminates without being entitled to do so has not just failed to end the contract. They have repudiated it, and the builder can accept that repudiation and sue for what it would have earned had it been allowed to finish.

The measure of damages follows from that. The court's task was to determine the sum the builder would have recovered had it been given the opportunity to complete the works, applying the principle in Robinson v Harman that the innocent party is to be placed, so far as money can do it, in the same situation as if the contract had been performed.

04The work really was defective

This is the part that makes the outcome worth understanding. The owners were not imagining the problems.

It would be easy to read the result as a court finding for the builder on the merits of the work. It did not. A portion of the works was held defective, the builder was held liable for the cost of rectifying it, and $574,380.41 including GST was deducted from what the builder recovered.

The defects were argued item by item against a joint experts' report running from JER 2 to JER 36. Two experts gave evidence, one retained by each side. The court worked through every disputed item and wrote a separate allowance for each.

$574,380.41
Rectification allowed
incl GST, deducted from the builder's damages
6
Items that recovered nothing
including the two largest claims
$10
Lowest award on a proven defect
half a million dollars was claimed on it
Two separate questions

Whether the work is defective, and whether you are entitled to end the contract, are decided separately. Winning the first does not win the second. These owners won the first and lost the second, and the second was worth far more than the first.

05Claimed against allowed

The three largest claims in the case, and what the court did with them.

Figure 1 · The three largest claims, as claimed and as allowed
Windows and doors $987,805.60 claimed Nil allowed First floor ceiling heights $511,216.06 claimed $10 allowed Concrete finish $123,458 claimed Nil allowed BAR = CLAIMED TICK = ALLOWED

Those three items carried $1,622,479.66 of the owners' case between them. The court allowed ten dollars.

None of the three failed because the builder proved its work was good. Each failed on the evidence put forward to prove the claim.

06Every item that recovered nothing

Six items, and the reason each one failed in the court's own words.

Item
Claimed
Why it failed
Windows and doors
$987,805.60
Not satisfied they failed the contractual requirement to be "commercial grade", so "the Owners' claim must fail". On the alternative arguments, "in the absence of such evidence" the court was not satisfied replacement was needed to obtain an occupancy permit. [456]–[457], [479]–[480]
Concrete finish, entertainment room
$123,458
The architect's instruction specifying no exposed aggregate arrived 16 days after the concrete was poured. "It is not open for the Owners to rely on a subsequent instruction to found a claim for damages in respect of this item." [515]–[516]
Ceiling deviating from straight
Low value
The photographs in the owners' building report "do not clearly show the alleged deviation", and "in the absence of any measurement in support of the deviation" the works were not defective as alleged. [580]
Veranda posts
Low value
Not satisfied that cracking in an ironbark post "constituted a defect rather than a natural feature of ironbark posts", or that it was attributable to anything the builder did. [623]–[624]
Staircase positioning
Low value
Not satisfied on the balance of probabilities that the work as constructed was a defect at all.
Hebel panel base
Low value
Already covered by the rectification allowed on the panel-support item. "I make no further allowance for rectification costs in relation to this item."
Read the reasons, not the items

One failed because a photograph was offered where a measurement was needed. One failed because the instruction post-dated the pour. One failed because the contractual standard was never proved. One failed because a natural characteristic of a timber species was called a defect. Not one of them turned on the quality of the building work.

07The ten dollar defect

The defect was real, the ceilings were genuinely too low, and the award was ten dollars.

The architectural drawings specified a ceiling height of 3000 mm. The first floor ceilings were built lower. That much was common ground.

Rectifying it meant procuring additional timber frames, reconstructing the roof and reinstalling the fabric of the house. The owners' expert estimated $511,216.06. Even the builder's expert put it at $230,262.

What was claimed

$511,216.06

  • Rebuild the roof structure
  • Additional timber frames
  • Reinstate the fabric of the house
What was awarded

$10

  • Rectification out of all proportion
  • Measure moves to diminution in value
  • No evidence of diminution was led
Stynes J[539]
In my view, this is a clear example where the cost of the proposed rectification is unreasonable, being out of all proportion to the benefit to be obtained. The authorities suggest that in such a case an appropriate measure of damages is the diminution in the value of the work occasioned by the breach. As the Owners lead no evidence of any diminution in the value of the property occasioned by this breach, I award nominal damages in the sum of $10.
Hale Corp Pty Ltd v Ng [2026] VSC 492, 31 July 2026
The missing document was a valuation

Once rectification is out of all proportion, the law offers a second measure: what the defect did to the value of the property. That measure was available the whole time. A valuer would have answered it. Nobody obtained one, so the second measure sat unproven and the award fell to a nominal sum.

08The defects everyone agreed on, worth nothing

Four items the experts agreed were defects. No costing was provided for any of them.

The judgment has a short section headed "Defect items for which no costing was provided". The experts agreed each of these items was a defect. No rectification method and no costing were put forward, so the court did not consider them further.

Item
Agreed a defect
What happened
Tiled grout lines
Yes
Treated as part of the water stop rectification. Not considered further.
Window reveals
Yes
Already rectified. No claim for rectification costs was made. Not considered further.
Window gasket seals
Yes
No claim for rectification costs was made. Not considered further.
Cracked tile
Yes
Already rectified. No claim for rectification costs was made. Not considered further.
An agreed defect is worth nothing until somebody costs it

Nobody disputed these were defects. Both experts accepted it. They still produced no recovery, because a court cannot award a number that no one has put in front of it. A report that identifies a defect and stops there has done half the job.

09What the court did allow

Twenty items were allowed. The pattern in the wins is as useful as the pattern in the losses.

The same report that lost the two largest items also won twenty smaller ones. Where an estimate was specific and reasoned, it was accepted, often in full.

Item
Allowed
Note
Prefinished timber flooring
$246,460
excl GST, no further contingency
Hebel panels, insufficient support
$95,968
"the only clear articulation of the costs"
No water stop angles installed
$71,028.60
allowed without a margin
Marble bench top
$11,695
Stone pillars out of square
$8,530 + $1,045
the expert's arithmetic error corrected by the court
Aluminium panelling
$8,450
rectification method trimmed
Rust stains to Hebel panels
$6,890
Timber lintel stud support
$5,176.40
Plaster finishes
$3,580
Surface water drainage
$3,280
Insufficient gutter clips
$2,720
Scratches to cabinetry doors
$2,280
Timber flooring short of the wall
$1,672.76
Wall deviates from straight
$1,660
External tiling
$1,200
External timber ceiling panelling
$714
Chipped tile
$680
Gutter holding water
$680
Overflows for box gutters
$505
the builder's expert's figure, one gutter
Polished concrete short of the wall
$300
the builder's expert's estimate accepted
Pressure flashings
Reduced
area figures taken from the builder's expert

Unless noted, each allowance carries a further 10% for contingencies plus GST. The total came to $522,164.01 excluding GST, or $574,380.41 including GST.

Stynes J[562]
I accept the estimate prepared by [the owners' expert], being the only clear articulation of the costs involved in that work, as a reasonable estimate of the rectification costs. I will allow rectification costs of $95,968 plus an allowance for contingencies of 10% and GST.
Hale Corp Pty Ltd v Ng [2026] VSC 492, 31 July 2026. The experts are named in the judgment; we do not repeat their names.

The phrase doing the work is the only clear articulation of the costs involved. It was accepted because it was specific, it was reasoned, and nothing else in the evidence did the job.

10What a report has to do

Drawn from what this court accepted and what it refused, item by item.

The six things this judgment rewarded
  1. Measure it, do not just photograph it. The deviation item failed because the photographs "do not clearly show the alleged deviation" and no measurement was provided.
  2. Name the standard the work fails. The largest claim in the case collapsed because the contractual standard, "commercial grade", was never proved to have been breached.
  3. Cost every item, including the agreed ones. Four agreed defects recovered nothing because no costing was provided.
  4. Show the workings. One item was reduced because the calculations of area were never supported. Another was corrected for an arithmetic error.
  5. Justify the method, not just the price. Rectification scope was trimmed where the evidence did not justify removing tiles and timber lining.
  6. Where rectification is disproportionate, value the loss instead. That is the difference between $511,216.06 and $10.

We are not suggesting the outcome would have been different with a different report, and nobody could honestly claim that. What the reasons set out, unusually clearly, is what a court needed and did not get — and that is a standard anyone commissioning a report can hold their consultant to before a dispute begins.

We don't just do inspections. We investigate.

11Before you end a building contract

The practical order of operations, and the one step that is not ours to give.

Get legal advice before you terminate, not after

Whether a particular contract can lawfully be ended depends on its own terms and on what has actually happened between the parties. That is a question for a lawyer, and it is not one this article, or any building consultant, can answer for you. These owners ended their contract and the court held that in doing so they repudiated it. The cost of asking first is very small against $697,805.38.

What a building consultant can do is put you in a position to get useful advice, and to prove your case if it comes to that. In practical order:

The order that works
  1. Document the defects independently while the work is still there to inspect. Measurements, the standard each item fails, and a costing for every item.
  2. Keep the paper trail. What the builder was told, when, and what it did in response. The termination in this case turned on the builder having answered the notice.
  3. Take legal advice on the contract before serving anything. A notice served on the wrong basis can be worse than no notice at all.
  4. Where rectification would be disproportionate, get a valuation as well. Otherwise the alternative measure of damages sits there unproven.
  5. Check who you are engaging. Ask whether the consultant has given evidence before, whether their reports quantify rectification item by item, and whether they will stand behind the report if it is tested.
Get an independent expert report before you act on a building dispute
We don't just do inspections. We investigate.
Request an expert witness report
Every job is quoted. Or contact us to talk it through first.

12Sources

  1. Hale Corp Pty Ltd v Ng [2026] VSC 492
    Supreme Court of Victoria, Commercial Court, Technology, Engineering and Construction List. Stynes J. Heard 1–2, 6–9, 13 and 16 October 2025; judgment 31 July 2026. Figures and quotations at [344], [349], [425]–[426], [456]–[457], [479]–[480], [515]–[516], [539], [562], [580], [623]–[624], [738], [871]–[873] and [917]. Each allowance is taken from the court's own reasons for that item. The parties' experts are named in the judgment; we have not repeated their names.
  2. Law Library Victoria, Library Bulletin, Issue 14
    8 August 2026 · lawlibrary.vic.gov.au
  3. Robinson v Harman (1848) 1 Exch 850
    The measure of damages for breach of contract, cited in the reasons at [874].
  4. Bellgrove v Eldridge (1954) 90 CLR 613
    Cost of rectification, and the limit where rectification is out of all proportion to the benefit obtained.
  5. Victorian Civil and Administrative Tribunal Act 1998 (Vic), section 77
    The power under which the proceeding was struck out and referred to the Supreme Court · legislation.vic.gov.au

Our Blog

YOUR GO-TO RESOURCE HUB

Whether you’re on the hunt or have already settled in, we’ll arm you with the know-how and confidence to keep your home safe and compliant. With our guidance, you can make informed decisions and steer clear of common pitfalls.

SEE ALL